Voyages to the House of Diversion 
Seventeenth-Century Water Gardens and the Birth of Modern Science

March 2018 - Opening it up even further


Back to Introduction and Contents


Once the  snow had melted it was time to return to what was a rather soggy site and plan the next stage of work.  The spread of destruction material already revealed along the  north edge of the circular mound suggested that there was plenty more to be uncovered and more that can be seen at once the greater then likelihood that we would make sense of it all, Accordingly the existing trench to the north was extended by a further metre, an area of 20 square metres to the west was marked out with the intention of picking up any in-coming water supply for fountains and what have you and  a metre wide trench was projected to the south to give a section right through the central area and up to the bank beyond. Unfortunately this meant, as it often does, moving part of a spoil heap and plenty of de-turfing, not that most of it was what you could really describe as turf.


March

the plan of the water parterre originally surveyed in 2014 with the current excavation outlined in red.









March     March
Ian sets to to shift some spoil and later in the week Peter and Ian lend a hand to remove turf and topsoil.




March

Plus in the first week of March: the lonely swan, lonely no more.



Unfortunately we had another wet weekend so when we returned to the site the lower portion of the dig was awash and everything was sticky. We were able to remove some topsoil by periodically scraping the mud off on the side of the barrow, not ideal digging conditions. However, on Friday the sun shone pretty well all day so we were able to to shift the trays and boxes of finds out from the corner where they had been sheltering and start to fell trees and prune branches ready to begin leveling the site for the concrete slabs which will form the base of the new finds sheds.




March     March
Up on the central island it's pretty wet but the ditch section is only fit for ducks.



March     March
More windy weather brought down the remains of another tree, you can see why we don't like to linger once the wind gets up, never mind, the sun shone whilst we got cracking on the shed site.




The third week in March was pretty productive, decent weather plus extra help meant that we were able to complete shifting the topsoil from the extension of the excavated area to the west and make good progress towards uncovering the the spread of destruction debris in the upper part of the ditch fill. Plus after much carrying of desperately heavy concrete slabs we were able to lay the best part of of the base for the new finds sheds as well as making a start on the long overdue task of sorting and reviewing finds from the past six years of digging.



March     March
Peter and Annie make a start on uncovering the ditch fill... and here it comes. loads more rubble, tile and plaster.






March     March
Bases are laid up at the observatory and a start is made on sorting through the finds




March    
..and here are a few more finds recovered from the leveling operation for the base of the sheds, everything from the fifteenth through to the twentieth centuries.



The last week in March was wet, not drenchingly so but persistently damp and slippy underfoot, not good working conditions so it was no surprise that labour was a bit thin on the ground. Even so we managed to take a significant slice out of the ditch fill to the west revealing some interesting ceramic material. In addition a further spread of rubble was uncovered when the trench to the north was extended by another metre. Finally the last remnants of topsoil were stripped from the long southern section so that after Easter it can be all hands to the trowels.




March
Too sticky and slippy for a wheelbarrow, excavations on the western portion of ditch which recovered ...



March    
... another interesting piece of 'architectural' terracotta and an almost complete and curiously marked roof tile.




March     March
The northern extension was just hard graft: before and two tonnes of damp clayey soil after.




March
The last of the topsoil on its way out, still plenty of roots to remove.