Voyages to the House of Diversion 
Seventeenth-Century Water Gardens and the Birth of Modern Science


July 2020 - Back in Business


Back to Introduction and Contents




After Christmas I had planned to take a bit of a break in order to make some significant progress on writing up the D. Phil thesis, this went pretty well and I was up to around 40,000 words by the second week in February and looking forward to taking a break from writing and getting back to digging when.... along came Corona Virus, Covid 19 and lock down. Tragedy for the world in general but this did mean that I could press on with the thesis and ended up with 78,000 words by the end of May. The end was in sight, nevertheless it was with enormous pleasure that on Wednesday July 8th. 2020 we were able to reopen the site and return to work at Hanwell. By the middle of the month not only had we been able to resume excavations on some of the areas opened last year that needed finishing but also bring in the digger and start clearance prior to beginning work on the eastern side of the island, a huge step forward.



July 2020
This is what an excavation looks like after being abandoned for several months



July     July
And here's Chris, Ian and Peter working as a team to tidy up with the finished result including sparkling new barrier tape, what a treat.




July 2020
Digging on the south west side of the island was less than sparkling as there was a winter's worth of mud to clear.




     July 2020
Nevertheless we persevered and amongst the latest crop of finds was this fragment of a very fine early seventeenth-century pedestal bowl... not sure about the social distancing here chaps....




July 2020     July 2020
Ian meanwhile was investigating our third dog burial. Initially a few bones were noted protruding from an eroded section edge. They looked remarkably like the finger or toe bones belonging to a child so we were on standby
 to call the police and coroner's office in when we found the first claw... it was a dog, relief all round.




July 2020
 A couple of days pumping  lowered the water along the northern side sufficiently to think about getting to work catching up with some section drawing.




July 2020     July 2020
On the south side tidying up the surface of the silting within the moat uncovered another crop of pots, four at least and one fine glass bowl. For a moment I thought we might have our first not only complete but intact pot
but a little more digging is needed before we celebrate that particular milestone. Up top the digger moves in to strip topsoil from the south east area.




July 2020     July 2020
Here's progress over two days, topsoil and the cleaner upper levels of silting in the moat removed by machine, all, of course, 'under direct archaeological supervision' as I'm continually writing in WSIs.




July
The campaign to catch up on recording continued with Verna finishing drawing the very first section we started to cut back in 2017




July.     July.
In the new area opened up we began by identifying the line of the wall and the the surface of the spread of demolition rubble. As part of this some serious attention had to be given to two stubborn tree stumps and attached roots... thanks Peter




July.     July.
Verna and Chris were back on the south side where there is still work to do removing the lowest levels of rubble and silt but Chris was later promoted to wall duty.




July     July
Almost got social distancing cracked and Andries nails the final corner of our octagon.



In preparation for the influx of diggers at the start of August one of the less pleasant tasks was to pump out and then scrape up a winter's worth of accumulated dead leaves nicely mixed into a thick sticky, smelly black goo. Not a job to pass on so I spent a couple of days  mired in the mud, no problems with social distancing now. As something of a reward I came across, in the eroded section edge, the remaining portion of  the rather fine seventeenth-century delftware plate we partially recovered last year, rather lucky I think. Work continued to  ensure we had access to as much of the site as possible so we could really spread people around. Preparations also included a little tree felling and then the assembling of individual tool kits so volunteers would not have to share equipment... strange times indeed.




July
Happy as a .... don't say it.... alright.... 'pig in muck'.





July     July
The reward... yes, it matches, now where did I put that tube of glue?




July     July
Juggling planks to create access whilst Chris comes across another pot, not a form we've seen before this one.




July
Our least favourite tree stripped and ready for the chop, the plan being that we will now be able to extend the trench a little and recover the rest of the fountain bowl... well that's the plan




July
Another dangerously leaning tree was felled.




July
Meanwhile Verna was master-minding the division of tools and equipment: ten new buckets, ten trowels, ten hand shovels, ten kneelers and ten hi-viz jackets, all ready to go.